Sharp Sand Calculator

Calculate sharp (grit) sand for paving bedding courses, screeds and concrete blends at 1.6 t/m³. Enter your area and the compacted layer thickness for tonnes and bulk bag quantities.

FreeInstant resultsUK planning data

Advanced calculator

Sharp Sand Calculator

1

Project setup

Start with a preset or configure everything yourself.

2

Area and shape

Use the shape that most closely matches the area you are covering.

3

Depth and ordering allowance

Depth has a large effect on quantity. Use the finished compacted depth where relevant.

Advanced options
Bag formats

More than one area?

Plan the whole project

Combine areas and layers, then see an order total for each material.

Open project planner →

Converter

Tonnes ↔ cubic metres

1 m³ = — tonnes

Saved locally

Recent calculations

Your recent calculations stay in this browser.

Reference data

Material planning densities

Use supplier product data whenever available. These figures are planning defaults.

MaterialCategoryPlanning densityTypical rangeCompaction

Overview

The bedding course sits between sub-base and blocks — it is screeded, not compacted loose, so measure the finished thickness.

How the calculation works

Sharp sand weight = area × screeded thickness × 1.6 t/m³, so each 25mm per 10 m² adds 0.4 tonnes.

The same tonnage feeds concrete work: sharp sand is half of a standard 1:2:4-style blend with cement and gravel.

Bulk bags are filled by weight, so a nominally 'tonne' bag at 850kg covers about 10.6 m² at 50mm.

Worked example

A slabbed patio 25 m² uses a 30mm sharp sand bed under slabs on a full sub-base.

Volume = 25 × 0.03 = 0.75 m³. Weight = 0.75 × 1.6 = 1.2 tonnes.

A 10% allowance takes the order to 1.32 tonnes — two 850kg bulk bags with spare for jointing.

Sharp sand at a glance

  • Planning density1.60 t/m³
  • Typical range1.50–1.70 t/m³
  • CategorySand
  • CompactionUsually not applied
  • SourcePlanning value based on typical UK sharp sand bulk densities
  • Reviewed2026-08-16

Sharp sand coverage guide

DepthArea per tonneArea per 850kg bagWeight per m²
25mm25.0 m²21.3 m²40 kg
40mm15.6 m²13.3 m²64 kg
50mm12.5 m²10.6 m²80 kg
75mm8.3 m²7.1 m²120 kg
100mm6.3 m²5.3 m²160 kg
150mm4.2 m²3.5 m²240 kg

Assumptions and accuracy

1.6 t/m³ is a planning value for dry-ish coarse grit sand; wet deliveries run heavier.

Screed and concrete quantities also depend on the cement and aggregate components calculated separately.

Confirm final quantities with your supplier, especially for screeds with strict level tolerances.

How to use this calculator

  • Measure the area to be bedded.
  • Enter the screeded sand thickness (30-50mm is typical under slabs and blocks).
  • Keep sharp sand selected — its coarse grading is what locks paving down.
  • Add a small allowance for edge losses and levelling.

When sharp sand is commonly used

Sharp sand beds block paving and natural stone slabs, forms floor screeds with cement, backfills trenches above pipe bedding, and provides grit for snow topping and play pits.

Frequently asked questions

How much sharp sand do I need for paving?

For a 50mm bedding course allow 80kg per square metre; at 30mm allow about 48kg. Multiply by your area and add 5-10%.

How many bulk bags of sharp sand for 20 m²?

At 50mm deep, 20 m² needs about 1.6 tonnes plus allowance — two 850kg bulk bags.

Is grit sand the same as sharp sand?

Yes — 'grit sand', 'sharp sand' and 'coarse sand' all describe the angular washed sand used for bedding and concrete. Building (soft) sand is a different material.

Does sharp sand need compacting?

A bedding course is screeded level and lightly compacted before laying — over-compacting displaces it and loses the level. Compact the sub-base below thoroughly instead; that layer carries the load.